# The Wheelabrator Kemsley K3 Generating Station Order 2021, Paragraph 3: Notice of commissioning


(1) Notice of commencement of commissioning of Work No 1 must be given to the relevant planning authority within 7 days of the date on which commissioning is commenced.
(2) Notice of completion of commissioning of Work No 1 must be given to the relevant planning authority within 7 days of the date on which commissioning is completed.

---