Part 2 K3 GENERATING STATION APPROVED PLANS AND DOCUMENTS
(1) Title | (2) Reference | (3) Revision |
|---|---|---|
| Environmental Statement | March 2010 | |
| ES Addendum (Air Quality) | June 2013 | |
| ES Chapter 10 – Hydrology and Flood Risk – Supplementary Report | May 2017 | |
| ES Addendum | May 2018 | |
| Design and Access Statement | March 2010 | |
| Surface Water Management and Foul Drainage Design Philosophy | December 2016 | |
| Ecological Mitigation and Management Plan | JPP1804-MP-001d | July 2013 |
| Flood Risk Assessment | May 2019 | |
| Proposed (Permitted) Site Location Plan | 16315/A0/P/0060 | Rev N |
| Proposed Site Layout | 16315/A1/P/0100 | Rev U |
| Proposed Building Layout | 16315/A0/P/0105 | Rev L |
| Boundary Treatment | 16315/A0/P/0106 | Rev R |
| South East Elevation | 16315/A1/P/0110 | Rev U |
| North East Elevation | 16315/A1/P/0111 | Rev T |
| South West Elevation | 16315/A1/P/0112 | Rev U |
| North West Elevation | 16315/A1/P/0113 | Rev T |
| Proposed Structure for Air Cooled Condenser (URC) Elevations | 16315/A1/P/0121 | Rev N |
| Main Building – Proposed South East Elevation | 16315/A0/P/0125 | Rev K |
| Main Building – Proposed North East Elevation | 16315/A1/P/0126 | Rev K |
| Main Building – Proposed South West Elevation | 16315/A1/P/0127 | Rev L |
| Main Building – Proposed North West Elevation | 16315/A0/P/0128 | Rev K |
| Site Layout and Access | 16315/A1/P/0160 | Rev K |
| Typical Office and Staff Amenities Building (UYA) Floor Plans | 16315/A1/P/0171 | Rev H |
| Proposed Gatehouse Floor Plan | 16315/A2/P/0172 | Rev L |
| Site Sections | 16315/A0/0250 | Rev J |
| Proposed Drainage Layout | 16315/A0/0301 | Rev J |
| Proposed Levels Site Plan | 16315/A1/0600 | Rev H |
| Illustrative Visual 1 of 7 | 16315/P/0150 | Rev R |
| Illustrative Visual 2 of 7 | 16315/P/0151 | Rev P |
| Illustrative Visual 3 of 7 | 16315/P/0152 | Rev O |
| Illustrative Visual 4 of 7 | 16315/P/0153 | Rev Q |
| Illustrative Visual 5 of 7 | 16315/P/0154 | Rev O |
| Illustrative Visual 6 of 7 | 16315/P/0155 | Rev O |
| Illustrative Visual 7 of 7 | 16315/P/0156 | Rev R |
| Landscape Masterplan | 16315/A1/4.21 | Rev M |
| Fuel Bunker Level +2.0000m | 16315/A1/P/0220 | Rev D |
| Fuel Bunker Level +20.000m and Level +36.000m | 16315/A1/P/0221 | Rev E |
| Fuel Bunker Section A-A | 16315/A1/P/0222 | Rev C |
| Fuel Bunker Section B-B | 16315/A0/P/0223 | Rev C |
| Tipping Hall Layout Level +2.000m | 16315/A1/P/0201 | Rev E |
| Tipping Hall Section A-A | 16315/A1/P/0202 | Rev D |
| Overall Roof Layout Comparison Drawing | 16315/A1/P/0200 | Rev H |
| Lighting Discharges Report | 20020117LXI0019 | Rev C |
| External Lighting Technical Submission | 20020117LXJ0922 | Rev I |
| External Lighting Drawing | 20020117LXG0907 | Rev H |
| K3 External Lighting Strategy | ECO00047 Fig1 | - |
| Access Road - Proposed Proposed Internal Access Layout | 9163-0135-01-JNY9060 | Rev 01 |
| K3 Employment Strategy | March 2012 |