# The Wigan Borough Council (Scotman’s Flash, Wigan Canal Bridge) Scheme 2017 Confirmation Instrument 2018, Note: Explanatory note


(This note is not part of the Order)
This instrument confirms a Scheme to construct over the navigable waters of the Leeds Liverpool Canal, the bridge specified in the Schedule to this Scheme as part of the highway which they are proposing to divert and construct a new section thereof from its junction with A49 Goose Green to the Westwood Park Link Road, Poolstock in the Borough of Wigan.
The Secretary of State has modified this Bridge Scheme as follows:
1 In the opening paragraph on page 1 of the Order the word ‘scheme’ has been replaced by ‘Scheme’.
2 In the Schedule to the Scheme, the paragraph titled ‘Plans and Specifications of the Scotsman’s Canal Bridge’ the words ‘rev.A’ have been added after Plan Number H279/HCL/601.
3 In the Schedule to the Scheme, the paragraph titled ‘Plans and Specifications of the Scotsman’s Canal Bridge’, the title of the Order has been amended to ‘The Wigan Borough Council (Scotsman’s Flash, Wigan Canal Bridge) Scheme 2017’.
4 In the Schedule to the Scheme, the paragraph titled ‘Span(s)’ has been amended to ‘Single span bridge. Clear span between faces of abutments of 32.00 metres. Clear span between reinforced soil abutments of 25.3 metres’.
5 Drawing number H279/HCL/601 rev A has been replaced by H279/HCL/601 rev C.

---
Source: https://www.legislation.gov.uk/uksi/2018/381/note (the official version)