# The Willington C Gas Pipeline Order 2014, Article 12: Access to works

Extent: E+W+S

The undertaker may, for the purposes of the authorised development,—
(a) form and lay out means of accesses or improve existing means of access in the indicative locations specified in columns (1) and (2) of Schedule 3 (access to works) as shown coloured pink on sheets 1 to 7, 9 and 10 of the works plans; and
(b) form and lay out such other means of access or improve existing means of access at such locations within the works limits as the undertaker reasonably requires for the purposes of the authorised development.

---
Source: https://www.legislation.gov.uk/uksi/2014/3328/article/12 (the official version)
Page: https://openlegislation.uk/willington-c-gas-pipeline-order-2014/article-12
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.