# The Willington C Gas Pipeline Order 2014, Paragraph 17: Control of noise during construction and maintenance

Extent: E+W+S

(1) No stage of the authorised development must commence until a written scheme for noise management during construction and maintenance of that stage has been submitted to and approved, in writing, by the relevant planning authority. The scheme must be based on the assessment and mitigation proposals contained in chapter 10 of the environmental statement with reference to BS5228 (code of practice for noise and vibration control at construction and open sites).
(2) The scheme must set out the particulars of—
(a) the works and the method by which they are to be carried out;
(b) the noise-attenuation measures to be taken to minimise noise resulting from the works, including any noise limits; and
(c) the provision of mitigation and, where relevant, agreed compensation terms for noise disturbance.
(3) The construction and maintenance works must be undertaken in accordance with the approved scheme except to the extent that a variation to the scheme is approved by the relevant planning authority in writing.

---
Source: https://www.legislation.gov.uk/uksi/2014/3328/schedule/1/paragraph/17 (the official version)
Page: https://openlegislation.uk/willington-c-gas-pipeline-order-2014/schedule-1/paragraph-17
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.