# The Willington C Gas Pipeline Order 2014, Paragraph 4: Detailed design approval

Extent: E+W+S

(1) No stage of the authorised development must commence until details of the layout, scale and external appearance of the following works within that stage (including any consultation responses from the Environment Agency, for those parts of the authorised development within the flood risk area and from the county council for the area of Works No.7 (the Yoxall Temporary Works Compound)) have been submitted to and approved, in writing, by the relevant planning authority—
(a) Works No.3 (the Yoxall AGI);
(b) Works No.7 (the Yoxall Temporary Works Compound), Works No.8 (the Carriers Road Temporary Works Compound) and Works No.9 (the Willington Power Station Temporary Works Compound), lay down and storage areas and facilities;
(c) the detailed pipeline route alignment; and
(d) the construction corridor, including additional working areas.
(2) The works described in sub-paragraph (1)(a) to (d) must be carried out in accordance with the approved details or any subsequent revisions that have been submitted to and approved, in writing, by the relevant planning authority.

---
Source: https://www.legislation.gov.uk/uksi/2014/3328/schedule/1/paragraph/4 (the official version)
Page: https://openlegislation.uk/willington-c-gas-pipeline-order-2014/schedule-1/paragraph-4
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.