  "url": "https://openlegislation.uk/willington-c-gas-pipeline-order-2014/schedule-1/paragraph-7",
  "json_url": "https://openlegislation.uk/willington-c-gas-pipeline-order-2014/schedule-1/paragraph-7.json",
  "legislation": "uksi/2014/3328",
  "legislation_title": "The Willington C Gas Pipeline Order 2014",
  "legislation_url": "https://openlegislation.uk/willington-c-gas-pipeline-order-2014",
  "path": "schedule/1/paragraph/7",
  "kind": "paragraph",
  "number": "7",
  "heading": "Construction traffic and highway accesses",
  "text": "(1) No stage of the authorised development (including the removal of roadside hedges) must commence until, for that stage, a written plan based on the transport statement section of the environmental statement has been submitted to and approved, in writing, by the relevant planning authority. The plan must include details of construction traffic and highway access arrangements and include copies of and take account of any consultation responses from the local highway authority.\n(2) The plan must contain details of the siting, design and layout of any new permanent or temporary means of access to a highway to be used by vehicular traffic, or any alteration to an existing means of access to a highway used by vehicular traffic.\n(3) The plan must if required by the local highway authority include details of the management measures to be employed at the highway accesses and construction car parking.\n(4) The plan must include details of all routes designated for construction delivery vehicles and must include details of a scheme for the signing of these routes. The designated routes must be based on those described in the transport statement within the environmental statement.\n(5) Throughout the period of the construction of the authorised development, vehicle wheel washing facilities must be provided as a minimum at the sites of Works No.7 (the Yoxall Temporary Works Compound) and of Works No.8 (the Carriers Road Temporary Works Compound). The written plan approved under sub-paragraph (1) must require that all construction vehicles must have their wheels cleaned before leaving the sites.\n(6) Subject to sub-paragraph (7), the construction traffic and highway access arrangements plan must be implemented as approved except to the extent that a variation to the plan is approved by the relevant planning authority in writing. Any submission to vary the approved plan must include copies of and take account of any consultation responses from the local highway authority.\n(7) Urgent works necessary on highway safety grounds, which would require a variation to the approved plan, may proceed following the sole approval, in writing, of the local highway authority.",
  "extent": "E+W+S",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 1 Pt. 2 para. 7 in force at 7.1.2015, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2014/3328/schedule/1/paragraph/7",
    "retrieved_at": "2026-10-28T23:53:21.816364+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}