# The Willington C Gas Pipeline Order 2014, Schedule 4: LAND IN WHICH SURVEYS AND INVESTIGATIONS MAY BE CARRIED OUT

Extent: E+W+S

(1)
(2)
1, 2, 3, 3B, 4, 4B, 5, 5B, 6, 6B, 8, 9, 9B, 10, 11, 11B, 12, 13, 14, 15, 16,17, 18, 19, 20, 21, 22, 23, 23B, 24, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38, 39, 40, 41, 42, 44, 45, 45B, 46, 47, 47B, 48, 49, 50, 51, 52, 53, 54, 55, 56, 57, 58, 59, 60, 61, 62, 63, 64, 65, 66, 67, 68, 69, 70, 71, 72, 73, 74, 75, 76, 77, 77B, 78, 78B, 79, 79B, 79C, 80, 81, 82, 83, 84, 84B, 84C, 85, 86, 87, 88, 89, 90, 90B, 90C, 91, 92, 93, 94, 95, 98, 99, 100, 101, 102, 102B, 102C, 102D, 103, 104, 105, 106, 107, 108, 108B, 109, 109B, 109C, 109D, 109E, 110, 110B, 110C, 111, 112, 113, 114, 119, 119B, 120, 121, 122, 123, 124, 125, 126, 127, 128, 128B, 129, 131, 131B, 132, 134, 134B, 134C, 134D, 135, 136, 137
Temporary rights of access, with or without vehicles, plant, apparatus and materials:
(a) to carry out soil tests, surveys (including environmental, ecological and archaeological surveys) and other investigation works including the making of trial holes and boreholes; and
(b) to carry out non-intrusive environmental wildlife surveys on the land and on each water body on the land including the assessment of habitats.
7
Temporary rights of access, with or without vehicles, plant, apparatus and materials:
(a) to carry out surveys and other investigation works (including environmental, ecological and archaeological surveys but excluding the making of trial holes and boreholes); and
(b) to carry out non-intrusive environmental wildlife surveys on the land and on each water body on the land including the assessment of habitats.
139
Temporary right of access, plant, apparatus and materials to carry out surveys and other investigation work (including environmental, ecological and archaeological surveys but excluding the making of trial holes and boreholes).
Those plots described in the book of reference prefixed with S
The right to access the land from time to time, with or without vehicles, to carry out non-intrusive environmental wildlife surveys on the land and on each water body on the land including the assessment of habitats.

---
Source: https://www.legislation.gov.uk/uksi/2014/3328/schedule/4 (the official version)
Page: https://openlegislation.uk/willington-c-gas-pipeline-order-2014/schedule-4
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.