# The Wireless Telegraphy (Licence Charges) Regulations 2020, Paragraph 5

Extent: E+W+S+N.I.

In this Part—
(a) “OMP” means the number corresponding to the number of the Operational Maximum Power (in Watts) as declared by the licensee on application for the earth station licence;
(b) “p” means the product of OMP multiplied by WBW; and
(c) “WBW” means the number corresponding to the number of the widest bandwidth (in MHz) as declared by the licensee on application for the licence.
Column 1: Range of p
Column 2: Fee (£) per earth station in the band 5.925–7.075 GHz
Column 3: Fee (£) per earth station in the band 13.78–14.5 GHz
Column 4: Fee (£) per earth station in any of the bands 27.5–27.8185 GHz, 28.4545–28.8265 GHz and 29.4625–30 GHz
0 < p ≤ = 100
500
300
200
100 < p ≤ = 2,500
2,400
1,400
800
p > 2,500
7,400
4,300
2,600

---
Source: https://www.legislation.gov.uk/uksi/2020/1068/schedule/4/paragraph/5 (the official version)
Page: https://openlegislation.uk/wireless-telegraphy-licence-charges-regulations-2020/schedule-4/paragraph-5
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.