# The Wrexham Gas Fired Generating Station (Correction) Order 2018, Introduction: Introductory text


Infrastructure Planning
Made 15th February 2018
Coming into force 16th February 2018
The Wrexham Gas Fired Generating Station Order 2017, which granted development consent within the meaning of the Planning Act 2008 (“the Act”) contains correctable errors within the meaning of the Act.
Before the end of the relevant period, as defined in paragraph 1(6)(a) of Schedule 4 to the Act, the Secretary of State received a written request from the applicant for the correction of errors and omissions in the Wrexham Gas Fired Generating Station Order under paragraph 1(5)(a) of Schedule 4 to the Act.
The Secretary of State has informed Wrexham County Borough Council, the planning authority for the area in which the land to which the Wrexham Gas Fired Generating Station Order relates is situated, that the request has been received in accordance with paragraph 1(7) of Schedule 4 to the Act.
The Secretary of State, in exercise of the powers conferred by paragraphs 1(4) and (8) of Schedule 4 to the Act, makes the following Order—

---
Source: https://www.legislation.gov.uk/uksi/2018/193/introduction (the official version)
Page: https://openlegislation.uk/wrexham-gas-fired-generating-station-correction-order-2018/introduction
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.