# The Wrexham Gas Fired Generating Station Order 2017, Paragraph 10: Travel plan during operational phase

Extent: E+W+S

(1) Prior to the date of final commissioning a written operational travel plan must be submitted to and approved by the relevant planning authority. Such operational travel plan to include—
(a) objectives and targets; and
(b) measures and initiatives to promote sustainable travel.
(2) The operational travel plan must be carried out as approved.

---