# The Wrexham Gas Fired Generating Station Order 2017, Paragraph 6: Piling

Extent: E+W+S

(1) No piling may commence until a piling strategy has been submitted to and approved by the relevant planning authority, such strategy to include a piling risk assessment, the results of such assessment and the piling techniques to be used in carrying out the authorised development.
(2) Piling must be carried out in accordance with the approved strategy.

---