# The Wrexham Gas Fired Generating Station Order 2017, Paragraph 21

Extent: E+W+S

In the event that any BT apparatus within or immediately adjacent to the Order land is likely to be placed at risk, either temporarily or permanently because of the movement of plant or equipment or both pursuant to the authorised development, the undertaker must contact a Network Alterations team representative.

---
Source: https://www.legislation.gov.uk/uksi/2017/766/schedule/9/paragraph/21 (the official version)
Page: https://openlegislation.uk/wrexham-gas-fired-generating-station-order-2017/schedule-9/paragraph-21
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.