# The Wrexham Gas Fired Generating Station Order 2017, Paragraph 70: Retained apparatus

Extent: E+W+S

(1) Not less than 56 days before the commencement of any specified work that does not require the removal of apparatus under paragraph 69 (removal of apparatus) the undertaker must submit to the solar operator a plan, section and description of the specified work to be executed.
(2) Those specified works must be executed only in accordance with the plan, section and description submitted under sub-paragraph (1) and in accordance with such reasonable requirements as may be made in accordance with sub-paragraph (4) by the solar operator for the alteration or otherwise for the protection of the apparatus, or for securing access to it.
(3) The solar operator is entitled to watch and inspect the execution of any specified work.
(4) Any requirements made by the solar operator under sub-paragraph (2) must be made within a period of 21 days beginning with the date on which a plan, section and description under sub-paragraph (1) are submitted to it.
(5) If the solar operator in accordance with sub-paragraph (4) and in consequence of the works proposed by the undertaker, reasonably requires the removal of any apparatus and gives written notice to the undertaker of that requirement, paragraph 69 (removal of apparatus) applies as if the removal of the apparatus had been required by the undertaker under paragraph 69(1).
(6) Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 56 days before commencing the execution of any specified work, a new plan, section and description instead of the plan, section and description previously submitted, and having done so the provisions of this paragraph apply to and in respect of the new plan, section and description.
(7) The undertaker is not required to comply with sub-paragraph (1) in a case of emergency but in that case it must give to the solar operator notice as soon as is reasonably practicable and a plan, section and description of those specified works as soon as reasonably practicable subsequently and must comply with sub-paragraph (2) in so far as is reasonably practicable in the circumstances.

---
Source: https://www.legislation.gov.uk/uksi/2017/766/schedule/9/paragraph/70 (the official version)
Page: https://openlegislation.uk/wrexham-gas-fired-generating-station-order-2017/schedule-9/paragraph-70
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.