The Building Safety Act 2022 (Commencement No. 4, Transitional and Saving Provisions) (Wales) Regulations 2024

W.S.I. 2024/207 · Made 22 February 2024 · Extends to England and Wales

Up to date with all changes known to legislation.gov.uk, revised to 1 July 2026.

Building And Buildings, Wales

Made 22 February 2024

The Welsh Ministers make these Regulations in exercise of the powers conferred on them by section 170(4)(a)(ii), (4)(a)(iii), (4)(a)(iv), (4)(a)(v), (4)(b)(iii), (4)(b)(iv), (4)(b)(v), (4)(b)(vi), (4)(b)(viii), (4)(b)(ix), (7) and (8) of the Building Safety Act 2022f1.

Annotations to the whole text

Footnotes

f1

2022 c. 30.

Contents

  1. 1Title and interpretation
  2. 2Provisions coming into force on 6 April 2024
  3. 3Transitional provision: approved inspectors who become registered building control approvers
  4. 4Transitional provision: approved inspectors who do not become registered building control approvers
  5. 5Transitional provisions: approved inspectors
  6. 6Regulation 6
  7. 7Regulation 7
  8. 8Transitional provision: higher-risk building work not commenced by 1 October 2024
  9. 9Transitional provisions: initial notices
  10. 10Regulation 10
  11. 11Transitional provision: new higher-risk building work
  12. 12Transitional provision: registered building inspector
  13. 13Saving provision: approved inspectors
  14. 14Saving provision: repeal of powers to make regulations
  15. Signature
  16. Schedule: The following provisions of Schedule 5 to the 2022 Act will not come into force on 6 April 2024 in accordance with regulation 2(d)(xi)—
  17. 1Paragraph 1
  18. 2Paragraph 2
  19. 3Paragraph 3
  20. 4Paragraph 4
  21. 5Paragraph 5
  22. 6Paragraph 6
  23. 7Paragraph 7
  24. 8Paragraph 8
  25. 9Paragraph 9
  26. 10Paragraph 10
  27. 11Paragraph 11
  28. 12Paragraph 12
  29. 13Paragraph 13
  30. 14Paragraph 14
  31. 15Paragraph 15
  32. 16Paragraph 16
  33. 17Paragraph 17
  34. 18Paragraph 18
  35. 19Paragraph 19
  36. 20Paragraph 20
  37. 21Paragraph 21
  38. 22Paragraph 22
  39. Explanatory note

1Title and interpretation

(1)

The title of these Regulations is the Building Safety Act 2022 (Commencement No. 4, Transitional and Saving Provisions) (Wales) Regulations 2024.

(2)

In these Regulations—

  • “the 1984 Act” (“Deddf 1984”) means the Building Act 1984f1;

  • “the 2022 Act” (“Deddf 2022”) means the Building Safety Act 2022;

  • “building work” (“gwaith adeiladu”) has the same meaning given in regulation 3 of the Building Regulations 2010f2.

(3)

For the purposes of regulations 3 and 4 of these Regulations, a registered building control approver is suitably qualified if the work they intend to carry out is within the scope of the registration of the registered building control approverf3.

(4)

Subject to paragraphs (2) and (3), expressions used in these Regulations and in the 1984 Act have the same meaning as in that Act.

2Provisions coming into force on 6 April 2024

The following provisions of the 2022 Act come into force on 6 April 2024—

(a)

section 32(3) (building control authorities) for all remaining purposes, so far as it relates to section 91ZD of the 1984 Actf1;

(b)

section 42 (regulation of building control profession), so far as it relates to inserting section 58Z2 into the 1984 Actf2;

(c)

paragraph 56 of Schedule 5 (minor and consequential amendments in connection with Part 3 of the 2022 Act);

(d)

in relation to Wales—

(i)

section 40 (liability of officers of body corporate);

(ii)

section 42 (regulation of building control profession) for all remaining purposes, except so far as it relates to sections 58Z7 and 58Z10 of the 1984 Act and inserting section 58Z2 into the 1984 Act;

(iii)

section 43 (transfer of approved inspectors’ functions to registered building control approvers);

(iv)

section 44 (functions exercisable only through, or with advice of, registered building inspectors) for all remaining purposes;

(v)

section 46 (higher-risk building work: registered building control approvers) for all remaining purposes;

(vi)

section 50 (cancellation of initial notice) for all remaining purposes;

(vii)

section 51 (new initial notices) for all remaining purposes;

(viii)

section 52 (information gathering) for all remaining purposes;

(ix)

section 53(2) and (3)(a)(ii) and (iii) and (3)(b) (information);

(x)

Schedule 4 (transfer of approved inspectors’ functions to registered building control approvers);

(xi)

Schedule 5 (minor and consequential amendments in connection with Part 3 of the 2022 Act) except for the paragraphs listed in the Schedule to these Regulations and subject to the exceptions in section 170(4)(b)(viii)(A) and (B) of the 2022 Act;

(xii)

Schedule 6 (appeals and other determinations) for all remaining purposes, subject to the exceptions in section 170(4)(b)(ix) of the 2022 Act.

3Transitional provision: approved inspectors who become registered building control approvers

(1)

This regulation applies where an approved inspectorf1 has become a suitably qualified registered building control approver before 6 April 2024 and has submitted an initial notice which has been accepted, or is deemed to be accepted, before 6 April 2024.

(2)

With effect from 6 April 2024, any initial notice submitted by the approved inspector before 6 April 2024 is treated as if it were given instead by that person in their capacity as a registered building control approver.

(3)

This regulation applies to initial notices relating to building work and higher-risk building workf2.

(4)

An approved inspector may continue to oversee higher-risk building work provided that—

(a)

the higher-risk building work is commenced before 1 October 2024, and

(b)

an approved inspector will continue to be a suitably qualified registered building control approver until completion of that higher-risk building work.

(5)

An approved inspector may continue to oversee building work that is not higher-risk building work.

(6)

For the purposes of this regulation, the approved inspector and registered building control approver must be the same legal person.

4Transitional provision: approved inspectors who do not become registered building control approvers

(1)

This regulation applies where an approved inspector has not become a suitably qualified registered building control approver before 6 April 2024.

(2)

Where an approved inspector is overseeing higher-risk building work before 6 April 2024, then—

(a)

an approved inspector must not continue to oversee higher-risk building work on or after 6 April 2024;

(b)

any initial notice submitted by the approved inspector in respect of higher-risk building work is cancelled;

(c)

responsibility for overseeing higher-risk building work will transfer to the local authority.

(3)

Where an approved inspector is overseeing building work that is not higher-risk building work, then—

(a)

until but not including 1 October 2024, an approved inspector may continue to oversee building work;

(b)

any initial notices submitted by the approved inspector will cease to be in force on 1 October 2024;

(c)

any building work that is not completed before 1 October 2024 will transfer to the local authority unless a registered building control approver, who is not the same person as the approved inspector, has submitted a new initial notice for that work and the notice is accepted or is deemed to be accepted;

(d)

until but not including 1 October 2024, an approved inspector may continue to issue a plans certificatef1, a final certificatef2, and an amendment noticef3 in respect of building work.

(4)

Where an amendment notice is issued before 1 October 2024 and that notice changes the nature of the building work specified in the initial notice so that it becomes higher-risk building work, such work must be transferred to the local authority.

5Transitional provisions: approved inspectors

Until but not including 1 October 2024, despite amendments made by section 46 of the 2022 Act, sections 52A and 55(2A) and (2E) of the 1984 Act have effect as if any reference to a registered building control approver were a reference to an approved inspector.

6

Until but not including 1 October 2024, despite amendments made by paragraphs 2 to 4 and 6 to 13 of Schedule 4 to the 2022 Act, sections 42(1), 47(1) and (5)(b), 50(7), 51(1), 51A(2)(a)(ii), 51C(2)(a), 52(1) and (2)(a), 56(5), 57(3), and 58(3) of the 1984 Act have effect as if any reference to a registered building control approver were a reference to an approved inspector.

7

Until but not including 1 October 2024, despite amendments made by paragraph 8 of Schedule 6 to the 2022 Act, section 50(2) of the 1984 Act has effect as if any reference to a registered building control approver were a reference to an approved inspector.

8Transitional provision: higher-risk building work not commenced by 1 October 2024

Where regulation 3(1) of these Regulations applies and higher-risk building work is not commenced before 1 October 2024, then—

(a)

the initial notice related to the higher-risk building work will cease to be in force on 1 October 2024 for the purposes of section 47(4)(b)(ii) of the 1984 Act, and

(b)

any plans certificate related to that initial notice will cease to be in force on 1 October 2024.

9Transitional provisions: initial notices

Where higher-risk building work has commenced before 1 October 2024, and the initial notice for that work is cancelled by the registered building control approver before, on or after 1 October 2024, responsibility for the higher-risk building work will transfer to the local authority on the day on which the initial notice is cancelled.

10

Where an initial notice for building work that is not higher-risk building work, is cancelled by an approved inspector or a registered building control approver before 1 October 2024, a different registered building control approver may submit an initial notice for that work.

11Transitional provision: new higher-risk building work

(1)

Any new higher-risk building work must be overseen by the F1building control authority on or after 6 April 2024.

(2)

Initial notices for higher-risk building work must not be submitted to a local authority by an approved inspector or a registered building control authority on or after 6 April 2024.

(3)

For the purposes of paragraph (1), new higher-risk building work means higher-risk building work which is not already detailed in an initial notice F2only relating to building work submitted and accepted, or deemed to be accepted, before 6 April 2024.

F3(4)

In paragraph (1), “building control authority” means the local authority as stated in section 121A of the Building Act 1984.

12Transitional provision: registered building inspector

(1)

Subject to paragraphs (2) and (3), a person may continue to work on buildings, or higher-risk buildings, until but not including 1 October 2024.

(2)

A person must be a registered building inspector before 6 April 2024f1.

(3)

A person—

(a)

must be in the process of having their competence assessed—

(i)

by an approved competence assessment scheme, and

(ii)

to the required level appropriate to the work they intend to carry out, or

(b)

has had their competence assessed to the required level appropriate to the work they intend to carry out and has applied to have their registration varied.

(4)

Where the register provides for different classes by virtue of section 58C(2) of the 1984 Act, and paragraphs (2) and (3) apply, those classes are to be disregarded until but not including 1 October 2024.

(5)

Paragraph (1) does not apply where, following the completion of a competence assessment, a person has failed their assessment at the required level appropriate to the work they intended to carry out.

13Saving provision: approved inspectors

Until but not including 1 October 2024, despite the omission of section 49 of the 1984 Act by paragraph 5 of Schedule 4 to the 2022 Act, section 49 continues to apply where regulation 4(1) applies and for the period during which an approved inspector may continue to oversee building work in accordance with regulation 4(3)(a) of these Regulations.

14Saving provision: repeal of powers to make regulations

Despite the omission of paragraphs 2 to 4B of Schedule 1 to the 1984 Actf1 by paragraph 83(3) of Schedule 5 to the 2022 Act, any provisions of the following regulations made under paragraphs 2 to 4B of Schedule 1 to the 1984 Act continue in force and have effect as if made under paragraphs 1A, 1B, 1C, 1D, 1F and 1G of Schedule 1 to the 1984 Act and may be varied or revoked accordingly—

(a)

the Building (Local Authority Charges) Regulations 2010f2;

(b)

the Building Regulations 2010;

(c)

the Building (Approved Inspectors etc.) Regulations 2010f3.

Signature

Julie James

Minister for Climate Change, one of the Welsh Ministers

22 February 2024

1

Paragraph 14(8).

2

Paragraph 15(10).

3

Paragraph 20.

4

Paragraph 21(3), (4), and (5).

5

Paragraph 22(3), (4), (5) and (6).

6

Paragraph 23(3) and (4).

7

Paragraph 24(3).

8

Paragraph 26(3) and (4).

9

Paragraph 27(3), (4) and (5).

10

Paragraph 28.

11

Paragraph 29.

12

Paragraph 31.

13

Paragraph 32.

14

Paragraph 40(2).

15

Paragraph 41(3).

16

Paragraph 42(2).

17

Paragraph 43.

18

Paragraph 45.

19

Paragraph 46(3).

20

Paragraph 55(3).

21

Paragraph 79.

22

Paragraph 90.

Explanatory note

(This note is not part of the Regulations)

These Regulations contain commencement, transitional and saving provisions made under the Building Safety Act 2022 (c. 30) (“the 2022 Act”).

Regulation 2 brings into force certain provisions of Part 3 of, and Schedules 4, 5 and 6 to, the 2022 Act on 6 April 2024. These provisions relate to the new regulatory regime for the building control profession.

Regulation 3 makes a transitional provision to provide that an approved inspector, who becomes a registered building control approver before 6 April 2024, may continue overseeing higher-risk building work on or after 6 April 2024.

Regulation 4 contains a transitional provision which provides that an approved inspector who does not become a registered building control approver must not oversee higher-risk building work on or after 6 April 2024. This regulation does, however, provide that an approved inspector may continue to oversee building work that is not higher-risk building work, for a limited time.

Regulations 5 to 7 make transitional provisions to ensure that references to registered building control approvers, inserted into the Building Act 1984 (c. 55) (“the 1984 Act”) by section 46 of, and Schedules 4 and 6 to, the 2022 Act, may be read as references to approved inspectors until 1 October 2024.

Regulation 8 contains a transitional provision related to the commencement of higher-risk building work. This regulation provides that where higher-risk building work is not commenced before 1 October 2024 by a registered building control approver, the initial notice and plans certificate related to such work will cease to be in force on 1 October 2024.

Regulations 9 and 10 make transitional provisions related to initial notices which are cancelled before 1 October 2024 in respect of building work, including higher-risk building work.

Regulation 11 contains a transitional provision for new higher-risk building work. This regulation provides that, on or after 6 April 2024, new higher-risk building work will be overseen by a local authority.

Regulation 12 makes a transitional provision to disregard the different classes of building inspector on the register and allows a person to continue working on buildings, including higher-risk buildings, until 1 October 2024. This regulation only applies where a person has registered as a building inspector and is in the process of having their competence assessed, or has successfully had their competence assessed, at the required level appropriate to the work they intend to carry out.

Regulation 13 makes a saving provision arising from the omission of section 49 of the 1984 Act to ensure that, until 1 October 2024, section 49 still applies to approved inspectors where the conditions in regulation 4(1) and (3) are met.

Regulation 14 makes a saving provision arising from the omission of paragraphs 2 to 4B of Schedule 1 of the 1984 Act.