Regulation 3 Transitional provision: approved inspectors who become registered building control approvers
England and Wales
This regulation applies where an approved inspectorf1 has become a suitably qualified registered building control approver before 6 April 2024 and has submitted an initial notice which has been accepted, or is deemed to be accepted, before 6 April 2024.
With effect from 6 April 2024, any initial notice submitted by the approved inspector before 6 April 2024 is treated as if it were given instead by that person in their capacity as a registered building control approver.
This regulation applies to initial notices relating to building work and higher-risk building workf2.
An approved inspector may continue to oversee higher-risk building work provided that—
the higher-risk building work is commenced before 1 October 2024, and
an approved inspector will continue to be a suitably qualified registered building control approver until completion of that higher-risk building work.
An approved inspector may continue to oversee building work that is not higher-risk building work.
For the purposes of this regulation, the approved inspector and registered building control approver must be the same legal person.
Annotations
Footnotes
- f1
See the definition of “approved inspector” in section 49 of the Building Act 1984.
- f2
See the definition of “higher-risk building work” in section 120I of the Building Act 1984.