Regulation 4 Transitional provision: approved inspectors who do not become registered building control approvers
England and Wales
This regulation applies where an approved inspector has not become a suitably qualified registered building control approver before 6 April 2024.
Where an approved inspector is overseeing higher-risk building work before 6 April 2024, then—
an approved inspector must not continue to oversee higher-risk building work on or after 6 April 2024;
any initial notice submitted by the approved inspector in respect of higher-risk building work is cancelled;
responsibility for overseeing higher-risk building work will transfer to the local authority.
Where an approved inspector is overseeing building work that is not higher-risk building work, then—
until but not including 1 October 2024, an approved inspector may continue to oversee building work;
any initial notices submitted by the approved inspector will cease to be in force on 1 October 2024;
any building work that is not completed before 1 October 2024 will transfer to the local authority unless a registered building control approver, who is not the same person as the approved inspector, has submitted a new initial notice for that work and the notice is accepted or is deemed to be accepted;
Where an amendment notice is issued before 1 October 2024 and that notice changes the nature of the building work specified in the initial notice so that it becomes higher-risk building work, such work must be transferred to the local authority.
Annotations
Footnotes
- f1
See the definition of “plans certificate” in section 50 of the Building Act 1984.
- f2
See the definition of “final certificate” in section 51 of the Building Act 1984.
- f3
See the definition of “amendment notice” in section 51A of the Building Act 1984.