(1) The undertaker must only work and access the licensed area within a defined and marked out area so as to limit personnel and plant access to the area of Works Nos. 2 and 3.
(2) Co-ordinates (in WGS84) and plan diagrams of the licensed area and access routes must be submitted to the MMO at least 4 weeks prior to the commencement of the licensed activity.
(3) Licensed activity must not commence before the approval of the co-ordinates and plan diagrams of the licensed area and access routes has been given by the MMO.

---