# The York Potash Harbour Facilities Order 2016, Paragraph 32: Piling conditions

Extent: E+W

The undertaker must ensure that acoustic barriers are positioned—
(a) along the embankment between the lagoon and the construction works for the quay; and
(b) between the lagoon and the construction works for the conveyor constructed in the northern corridor.

---
Source: https://www.legislation.gov.uk/uksi/2016/772/schedule/5/paragraph/32 (the official version)
Page: https://openlegislation.uk/york-potash-harbour-facilities-order-2016/schedule-5/paragraph-32
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.