# The York Potash Harbour Facilities Order 2016, Paragraph 34: Capital dredging, disposal conditions and debris

Extent: E+W

(1) The undertaker must agree a capital dredge and disposal strategy with the MMO at least 4 weeks before the commencement of any licensed activities.
(2) If any disposal or dredging activities are to take place after 1st October 2017—
(a) the undertaker must submit a sediment sampling plan to the MMO for approval at least 6 months prior to that dredging or disposal activity being carried out;
(b) the sediment sampling and analysis of the sediment must be completed by a laboratory validated by the MMO at least 6 weeks prior to the dredging or disposal activity being carried out; and
(c) the dredging and disposal activity must not be carried out without the consent of the MMO.

---
Source: https://www.legislation.gov.uk/uksi/2016/772/schedule/5/paragraph/34 (the official version)
Page: https://openlegislation.uk/york-potash-harbour-facilities-order-2016/schedule-5/paragraph-34
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.