# The York Potash Harbour Facilities Order 2016, Paragraph 42: Capital dredging, disposal conditions and debris

Extent: E+W

In the event that the MMO becomes aware that any of the materials on the audit sheet cannot be accounted for, it must require the undertaker to carry out a side-scan sonar survey to plot all obstructions across a reasonable area of search agreed by the MMO where construction works and related activities have been carried out. Any obstructions that the MMO considers to be associated with the authorised development must be removed at the undertaker’s expense.

---