# The York Potash Harbour Facilities Order 2016, Paragraph 7: Lagoon habitat enhancement

Extent: E+W

(1) The lagoon habitat enhancement works must not commence until a written lagoon habitat enhancement plan (to include details of pre and post construction monitoring) has been submitted to and approved by the MMO (following consultation with Natural England, the Environment Agency and the local planning authority).
(2) The lagoon habitat enhancement plan must include—
(a) details of proposals for pre and post construction monitoring;
(b) details of the enhancement of habitat in the lagoon for water birds and a construction method statement regulating the construction of those works; and
(c) a timetable for the implementation of those works.
(3) The lagoon habitat enhancement plan (including pre and post construction monitoring information) must accord with the mitigation and monitoring strategy.
(4) The lagoon habitat enhancement plan must be implemented as approved.

---
Source: https://www.legislation.gov.uk/uksi/2016/772/schedule/5/paragraph/7 (the official version)