# The York Potash Harbour Facilities Order 2016, Paragraph 10: Further provisions about works

Extent: E+W

(1) Where temporary crossings for construction traffic are to be used, other than where the pipelines are under a carriageway of adequate standard of construction, then the crossing points must be suitably reinforced with sleepers or road plates or a specially constructed reinforced concrete raft or by installing a temporary bridge over the pipeline as necessary.
(2) Details of proposed temporary crossing points referred to in sub-paragraph (1) must be notified to the owner and operator of the pipeline in accordance with paragraph 4.

---
Source: https://www.legislation.gov.uk/uksi/2016/772/schedule/9/paragraph/10 (the official version)
Page: https://openlegislation.uk/york-potash-harbour-facilities-order-2016/schedule-9/paragraph-10
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.