# The York Potash Harbour Facilities Order 2016, Paragraph 4: Authorisation of works details affecting pipelines or protected crossings

Extent: E+W

(1) Before commencing any part of a relevant work the undertaker must submit to the owners and any operators of any affected asset the works details and obtain a written acknowledgement of receipt of those works details from the specified persons in relation to the affected asset concerned.
(2) The undertaker must as soon as reasonably practicable provide such further particulars as the owner or operator of any affected asset may, within 45 days from the receipt of the works details under sub-paragraph (1), reasonably require.

---