# The York Potash Harbour Facilities Order 2016, Paragraph 5: Authorisation of works details affecting pipelines or protected crossings

Extent: E+W

No part of a relevant work is to be commenced until one of the following conditions has been satisfied—
(a) the works details supplied in respect of that relevant work under paragraph 4 have been authorised by the owner and operator of all the affected assets; or
(b) the works details supplied in respect of that relevant work under paragraph 4 have been authorised by an expert under paragraph 7(3); or
(c) authorisation is deemed to have been given in accordance with paragraph 7(1).

---
Source: https://www.legislation.gov.uk/uksi/2016/772/schedule/9/paragraph/5 (the official version)
Page: https://openlegislation.uk/york-potash-harbour-facilities-order-2016/schedule-9/paragraph-5