# The York Potash Harbour Facilities Order 2016, Paragraph 8: Notice of works

Extent: E+W

The undertaker must provide to the owner and operator of an affected asset a minimum of 28 days’ notice prior to commencing any relevant work in order that an engineer can be made available to observe the relevant works and, when required, advise on the necessary safety precautions.

---