Paragraph 4 Third Iteration EMPI1

England and Wales

(1)

Following completion of construction of the authorised development the Third Iteration EMP must be submitted to the Secretary of State for approval in writing, following consultation with the relevant planning authority and the Environment Agency on matters related to its functions.

(2)

The authorised development must be operated and maintained in accordance with the Third Iteration EMP as so approved.

Annotations

Commencement

I1

Sch. 2 para. 4 in force at 9.2.2024, see art. 1