Paragraph 92 Cathodic protection testingI1
England and Wales
Where in the reasonable opinion of the undertaker—
(a)
the authorised development might interfere with the existing cathodic protection forming part of a pipe-line; or
(b)
a pipe-line might interfere with the proposed or existing cathodic protection forming part of the authorised development,
CLH and the undertaker must co-operate in undertaking the tests which the undertaker considers reasonably necessary for ascertaining the nature and extent of such interference and measures for providing or preserving cathodic protection.
Annotations
Commencement
- I1
Sch. 9 para. 92 in force at 1.6.2016, see art. 1