Schedule 7 LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKENI1

England and Wales

(1)

Location

(2)

Plan reference number(s) shown on Land Plans

(3)

Purpose for which temporary possession may be taken

(4)

Relevant part of the authorised development

Land Plans – Sheet 1
In the administrative area of North East Lincolnshire Council1/1n, 1/1p, 1/1q, 1/5bRequired to provide construction working area and access for site traffic.All works
1/1s, 1/4b, 1/4cRequired for borrow pits to source material to construct raised sections of the new road construction.All works
1/1ae, 1/1al, 1/1amRequired to provide an area for topsoil and other construction material storage.All works
In the administrative area of North Lincolnshire Council1/1aRequired to enable the use of the existing access track between the A160, Ryehill Farm and A1077 Ulceby Road.Work No. 1
1/1b, 1/1c, 1/1d, 1/1e, 1/1f, 1/1h, 1/1i, 1/1j, 1/1k, 1/1m, 1/1u, 1/1v, 1/1w, 1/1x, 1/1z, 1/1af, 1/1ag, 1/1ai, 1/1aj, 1/2a, 1/3a, 1/3c, 1/3d, 1/3e, 1/3fRequired to provide construction working area and access for site traffic.All works
1/1t, 1/1akRequired for the diversion of an electric cable and associated apparatus.Work No. 9
1/1y, 1/1ahRequired for the diversion of electric cables and associated apparatus and to provide construction working area and access for site traffic.All works
Land Plans – Sheet 2
In the administrative area of North Lincolnshire Council2/1a, 2/2a, 2/5f, 2/5h, 2/5k, 2/8b, 2/10bRequired for the construction of accesses.All works
2/2b, 2/2cRequired for the diversion of a water pipeline and electric cable and associated apparatus, and required to provide construction working area and access for site traffic.All works
2/2eRequired to provide construction working area and access for site traffic and also the diversion of water pipeline and overhead electric cable.All works
2/2fRequired for the diversion of a water pipeline and electric cable and associated apparatus.Work Nos. 10 & 11
2/5a, 2/6aRequired for the diversion of up to 2 water pipelines.Work No. 12
2/5cRequired to provide construction working area and access for site traffic and also the diversion of up to 3 high pressure gas pipelines and the protection of an intermediate pressure gas pipeline.All works
2/5dRequired for the diversion of up to 3 high pressure gas pipelines and the protection of an intermediate pressure gas pipeline.Work No. 15, 16 & 17
2/5e, 2/5i, 2/5l, 2/5m, 2/7b, 2/7h, 2/7j, 2/9aRequired to provide construction working area and access for site traffic.All works
2/5j, 2/10cRequired to provide topsoil and other construction material storage areas.All works
2/6cRequired for the diversion of up to 3 high pressure gas pipelines and the protection of an intermediate pressure gas pipeline.Work Nos. 14, 15 & 16
2/7cRequired to provide topsoil and other construction material storage areas, and required to provide construction working area and access for site traffic.All works
2/7dRequired for the diversion of an electric cable and associated apparatus.Work No. 11
2/7eRequired for the provision of the main site compound to include, but not limited to, site offices, welfare facilities, parking provisions, storage of plant and materials and the treatment of site generated waste and also to provide construction working area and access for site traffic.All works
2/7fRequired to provide construction working area and access for site traffic and also the diversion of a high pressure gas pipeline.Work No. 14
2/7gRequired for the diversion of a high pressure gas pipeline.Work No. 14
2/8aRequired for the diversion of a high pressure gas pipeline.Work No. 17
Land Plans – Sheet 3
In the administrative area of North Lincolnshire Council3/1, 3/2aRequired for the construction of a new access and the stopping up of an existing access.All works
3/5b, 3/5dRequired for the construction of the diversion to the existing Public Right of Way and the construction of up to 3 new drainage culverts and head walls.All works
3/9cRequired for the construction of a new access.All works
3/9dRequired to provide an area for topsoil and other construction material storage.All works
Land Plans – Sheet 4
In the administrative area of North Lincolnshire Council4/1d, 4/1g, 4/1jRequired for the diversion of an oxygen pipeline.Work No. 30
4/1h, 4/3d, 4/6dRequired for the construction of accesses.All works
4/1i, 4/1kRequired to provide an area for topsoil and other construction material storage.All works
4/4a, 4/8Required to provide construction working area and access for site traffic.All works
4/5a, 4/5b, 4/5cRequired for the construction of a new bridge under the existing railway and for construction working area.Work No. 29
4/7Required for the provision of a secondary site compound to include, but not limited to, site offices, welfare facilities, parking provisions, storage of plant and materials and the treatment of site generated waste.All works