Schedule 6 LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN
(1) Plot reference Number shown on Land Plans | (2) Purpose for which temporary possession may be taken | (3) Relevant part of the authorised development |
|---|---|---|
| 1/2c, 1/2d | Required to provide construction access. | Work No. 17 |
| 1/2e | Required to provide construction access. | Work Nos. 17, 19 and 20 |
| 1/3a, 1/4a, 1/5b, 1/7b, 1/11, 1/12a | Required to provide an area for construction material storage and storage of plant. | All Works |
| 1/3a | Required to provide construction access. | Work Nos. 1, 2, 3, 8, 17, 18 and 19 |
| 1/4a | Required to provide construction access. | Work Nos. 20 and 21 |
| 1/5b | Required to provide construction access. | Work Nos. 1, 3, 7, 8, 19 and 20 |
| 1/7b | Required to provide construction access. | Work Nos. 8, 9 and 11 |
| 1/7d, 1/10h, 1/10i, 1/12b, 1/15a | Required to provide site access. | All Works |
| 1/10f | Required to provide construction access and site access. | Work Nos. 12, 13 and 25 |
| 1/14a, 1/14b, 1/15b | The main site compound to include, but not limited to, site offices, welfare facilities, parking provisions, storage of plant and materials, and the treatment of site generated waste. | Work No. 25A and 25B |
| 1/2f, 1/6 | Required to provide a perimeter enclosure and exclusion zone to allow for safe construction. | Work No. 8 |
| 2/1, 2/2a | Required to provide access to the site compound. | Work No. 25C |
| 2/2b | The main site compound to include, but not limited to, site offices, welfare facilities, parking provisions, storage of plant and materials, and the treatment of site generated waste. | Work No. 25C |