OpenLegislation

Paragraph 3 Construction Environmental Management PlanI1

England, Wales and Scotland

(1)

No authorised development is to commence until a CEMP has been submitted to and approved in writing by the relevant planning authority.

(2)

The CEMP must—

(a)

be substantially in accordance with the outline construction environmental management plan certified under article 38 (certification of plans, etc.);

(b)

contain a record of all the sensitive environmental features that have the potential to be affected by the construction of the proposed development;

(c)

incorporate the measures as detailed in the environmental report;

(d)

include information on the control measures required to mitigate and reduce potential impacts which reflect the mitigation measures included in sections 4 to 13 of the environmental report;

(e)

require adherence to working hours of 7:00am to 7:00pm on Mondays to Fridays and 7:00am to 1:00pm on Saturdays, except for—

(i)

works associated with changes to the traffic management layout;

(ii)

works associated with the construction of tie-ins at slip roads;

(iii)

works associated with concrete repairs to the existing A1058 structures at the A19 roundabout;

(iv)

works associated with bridge resurfacing and waterproofing of the Middle Engine Lane and Middle Engine Lane structures;

(v)

works associated with the medium pressure gas diversion across the A19 roundabout circulatory carriageway;

(vi)

works associated with providing drainage connections across the A19 carriageway at the A19/A193 Wallsend Junction from the north and southbound verges;

(vii)

works associated with traffic signal duct crossings and loops;

(viii)

any emergency works;

(f)

require adherence to working hours of 8:00am to 6:00pm on Mondays to Fridays for any works involving impact piling; and

(g)

include management plans, working methods and mitigation measures for each of the topics covered in the environmental report, including—

(i)

Air Quality Management Plan;

(ii)

Landscape Plan;

(iii)

Cultural Heritage Management Plan;

(iv)

Ecology Management Plan;

(v)

Materials Management Plan;

(vi)

Site Waste Management Plan;

(vii)

Noise and Vibration Management Plan; and

(viii)

Water and Drainage Management Plan.

(3)

The authorised development must be constructed in accordance with the approved CEMP.

Annotations

Commencement

I1

Sch. 2 para. 3 in force at 18.2.2016, see art. 1