Paragraph 23
At least 28 days prior to the commencement of Work No. 3 the undertaker must provide to ScottishPower Renewables copies of detailed design information for that work demonstrating that the safe manoeuvre of the Design Vehicle can be accommodated travelling from the east and turning through the same junction to travel back east.
If by the expiry of 28 days beginning with the date on which a plan or document under sub-paragraph (1) is submitted to it ScottishPower Renewables has not advised the undertaker in writing of any reasonable requirements for the alteration of the detailed design of that work in order to accommodate the safe manoeuvre of the Design Vehicle through the junction as described in sub-paragraph (1), it shall be deemed not to have any such requirements.
Work No. 3 must be constructed in accordance with the detailed design information referred to in sub-paragraph (1) and any reasonable requirements specified by ScottishPower Renewables in accordance with sub-paragraph (2) that are necessary to ensure the safe manoeuvre of the Design Vehicle through the junction as described in sub-paragraph (1).