Paragraph 24
At least 28 days prior to the commencement of Work No. 4 the undertaker must provide to ScottishPower Renewables copies of detailed design information and the detailed construction methodology for that work demonstrating—
that the safe manoeuvre of the Design Vehicle can be accommodated from the A30 eastbound through the Chybucca Junction to the existing A30;
that appropriate over-run areas will be provided; and
how access will be maintained to the Wind Farm throughout construction.
If by the expiry of 28 days beginning with the date on which a plan or document under sub-paragraph (1) is submitted to it ScottishPower Renewables has not advised the undertaker in writing of any reasonable requirements for the alteration of the detailed design of that work or the detailed construction methodology for that work in order to accommodate the safe manoeuvre of the Design Vehicle through the junction, ensure that appropriate over-run areas are provided or to maintain access to the Wind Farm during construction, as described in sub-paragraph (1), it shall be deemed not to have any such requirements.
Work No. 4 must be constructed in accordance with the detailed design information and the detailed construction methodology referred to in sub-paragraph (1) and any reasonable requirements specified by ScottishPower Renewables in accordance with sub-paragraph (2) that are necessary to accommodate the safe manoeuvre of the Design Vehicle through the junction, to ensure that appropriate over-run areas are provided or to maintain access to the Wind Farm during construction, as described in sub-paragraph (1).