Paragraph 25
At least 28 days prior to the commencement of Work No. 5 the undertaker must provide to ScottishPower Renewables copies of detailed design information for that work demonstrating—
that the safe manoeuvre of the Design Vehicle can be accommodated from the re-aligned existing A30 eastbound into the Wind Farm;
that appropriate over-run areas will be provided which will have a minimum 0.5m buffer either side of the theoretical design vehicle swept path;
in respect of Work No. 5(g)—
that a new site access gate and extensions with multi-lock system to match the existing site access gate will be provided;
that a minimum 5m running width on straight sections and wider on bends to accommodate the Design Vehicle has been accommodated;
that a minimum 0.5m verge width has been accommodated which will be increased to approximately 3m where it is required to include the realigned cables comprised within Work No. 5(m);
in respect of Work No. 5(m) that all realigned cables will be within the Order limits; and
that drainage works required as a result of Work No. 5 will be provided.
At least 28 days prior to the commencement of Work No. 5 the undertaker must provide to ScottishPower Renewables copies of the detailed construction methodology for that work demonstrating how access will be maintained to all parts of the Wind Farm throughout construction.
If by the expiry of 28 days beginning with the date on which a plan or document under sub-paragraph (1) or (2) is submitted to it ScottishPower Renewables has not advised the undertaker in writing of any reasonable requirements for the alteration of the detailed design of that work or the detailed construction methodology for that work in order to achieve the measures referred to in sub-paragraphs (1) and (2) it shall be deemed not to have any such requirements.
Work No. 5 must be constructed in accordance with the detailed design information and the detailed construction methodology and any reasonable requirements specified by ScottishPower Renewables in accordance with subparagraph (3) that are necessary to achieve the measures referred to in sub-paragraphs (1) and (2).