OpenLegislation

Paragraph 27

Original text. Later amendments are not shown.

(1)

Following construction of the over-run areas comprised within Work No. 4 and Work. No. 5, the undertaker will at its own cost and expense and insofar as it is the owner of and/or the highway authority for the areas in question—

(a)

keep the over-run areas clear of, without limitation, all rubbish, debris and vehicles, at all times;

(b)

undertake any clearance and/or maintenance required within reasonable timescales;

(c)

provide ScottishPower Renewables with copies of keys required to unlock any lockable bollards or similar that would prevent or hinder the use of the over-run areas; and

(d)

restrict access to those parts of the over-run areas where lockable bollards or similar are in place to the undertaker, the local highway authority and to ScottishPower Renewables only.

(2)

In the event that the existing re-aligned A30 is adopted the undertaker will use reasonable endeavours to procure that the local highway authority complies with the obligations under paragraph (1).