Paragraph 16 Delivery approach planI1

England and Wales

(1)

No part of the authorised development is to commence until a delivery approach plan for the construction of the authorised development has, after consultation by the undertaker with the local highway authority and relevant planning authority, been submitted to and approved in writing by the Secretary of State. The delivery approach plan must set how the authorised development will be delivered to ensure that mitigation works will be in place at the point when the works for which that mitigation is required are completed, which mitigation works include but are not limited to—

(a)

the landscaping approved under requirements 6 and 7;

(b)

the surface water drainage approved under requirement 13;

(c)

the noise mitigation approved under requirement 14; and

(d)

the highway lighting approved under requirement 15.

(2)

Where any requirement refers to any part of the authorised development and discharge is sought for a part, the delivery approach plan must set out how that part fits into the overall plan and why it is appropriate for that part to commence as a part.

Annotations

Commencement

I1

Sch. 2 para. 16 in force at 19.2.2021, see art. 1