Paragraph 33 I1
England and Wales
Before commencing the construction of, or the carrying out of any Works the undertaker must provide to the local highway authority the Design Detailing and the Other Detailed Information relating to those Works.
The undertaker must not commence construction of, or the carrying out of the Works in question until approval has been given by the local highway authority to the Other Detailed Information or the Other Detailed Information has otherwise been agreed in writing between the undertaker and the local highway authority.
The Works must not be constructed except in accordance with the Other Detailed Information as may be approved or agreed in accordance with sub-paragraph (2).
If within 28 days after the Other Detailed Information has been submitted the local highway authority has not approved or disapproved it or it has not been otherwise agreed, the local highway authority is deemed to have approved it as submitted.
Annotations
Commencement
- I1
Sch. 8 para. 33 in force at 19.2.2021, see art. 1