OpenLegislation

Paragraph 46 I1

England and Wales

(1)

When the undertaker considers that the Works have reached completion it must notify the local highway authority and must allow the local highway authority the opportunity to inspect the Works and the undertaker must give proper consideration to any representations that are made by the local highway authority.

(2)

The undertaker may not notify the local highway authority under sub-paragraph (1) until either—

(a)

a stage 3 safety audit has been carried out in respect of the Works in question in accordance with GG19 of DMRB and in the opinion of the undertaker any recommended works identified in the audit have been completed; or

(b)

if the Works in question were not subject to a safety audit, the local highway authority has been provided an opportunity to inspect the works and the undertaker has in its opinion completed any further works required to address any safety deficiencies or defects identified as a result of the inspection.

Annotations

Commencement

I1

Sch. 8 para. 46 in force at 19.2.2021, see art. 1