Paragraph 3 Second Iteration EMPI1
England and Wales
(1)
No part of the authorised development is to commence until the Second Iteration EMP in relation to that part has been submitted to and approved in writing by the Secretary of State, following consultation with the relevant planning authority, the Environment Agency, Natural England, and the relevant local highway authority so far as it is relevant to their respective functions.
(2)
The authorised development must be constructed in accordance with the Second Iteration EMP.
Annotations
Commencement
- I1
Sch. 2 para. 3 in force at 8.9.2022, see art. 1