Paragraph 3 Second Iteration EMPI1
England and Wales
No part of the authorised development is to commence until the Second Iteration EMP for that part, substantially in accordance with the First Iteration EMP, has been submitted to and approved in writing by the Secretary of State, following consultation with the relevant planning authority, Natural England and the Environment Agency on matters related to their statutory functions.
The Second Iteration EMP for a part of the authorised development must be produced in accordance with DMRB and so far as is relevant to that part of the authorised development, must reflect the mitigation measures required by the REAC and set out in the environmental statement and must include the following management plans and method statements as are applicable to the part of the authorised development to which it relates—
Site Waste Management Plan;
Materials Management Plan;
Soils Management Plan;
Arboricultural Method Statement;
Air Quality and Dust Management Plan;
Noise and Vibration Management Plan;
Energy and Resource Use Management Plan;
Biodiversity Net Gain Management and Monitoring Plan;
Biodiversity Net Gain Audit Report;
Invasive Non-Native Species Management Plan and Bio-Security Risk Assessment, including an Invasive Non-Native Species Method Statement;
Landscape and Ecological Management Plan;
Construction Communications Management Plan;
Pollution Prevention Management Plan;
Erosion and Sediment Management Plan;
Carbon Management Plan;
Emergency Response Plan for Flood Events;
Education, Employment and Skills Plan;
Inclusion Action Plan;
Construction Worker Travel and Accommodation Plan;
Badger Method Statement;
Piling Works Method Statement;
Earthworks Method Statement;
Topsoil Strip Method Statement;
Storage of Oil, Fuel and Other Potentially Hazardous Substances Method Statement;
Designated Refuelling and Maintenance Areas and Concrete Batching Method Statement;
Welfare of Staff Method Statement; and
Dewatering Management Plan.
The authorised development must be constructed in accordance with the Second Iteration EMP.
In this paragraph, “REAC” means the register of environmental actions and commitments contained in the First Iteration EMP.
Annotations
Commencement
- I1
Sch. 2 para. 3 in force at 22.10.2025, see art. 1