Paragraph 60 FencingI1

England and Wales

Where so required by the Engineer, the undertaker must, to the reasonable satisfaction of the Engineer, fence off a specified work or a protective work or take such other steps as the Engineer may require to be taken for the purpose of separating a specified work or a protective work from the waterway, whether on a temporary or permanent basis or both.

Annotations

Commencement

I1

Sch. 9 para. 60 in force at 22.10.2025, see art. 1