Article 8 Limits of deviationI1

England, Wales and Scotland

(1)

In constructing Work Numbers, 1, 4, 7, 9, 10, 11, 14, 15, 17, 28, 29, 32, 34, 35 36 and 40 the undertaker may—

(a)

deviate laterally from the centrelines shown on the works plans to the extent that the situation of the centreline is varied by up to a maximum of 3 metres either side of the centreline of that work as shown on the works plans;

(b)

deviate by up to 3 metres from the points of commencement and termination; and

(c)

deviate vertically from the levels of the authorised development shown on the engineering drawings and sections, to a maximum of 1 metre upwards or 1 metre downwards,

except that the maximum limits of vertical deviation do not apply where it is demonstrated by the undertaker to the Secretary of State’s satisfaction and the Secretary of State, following consultation with the relevant planning authority and the local highway authority, certifies accordingly that a deviation in excess of these limits would not give rise to any materially new or materially different environmental effects from those reported in the environmental statement.

(2)

In constructing or maintaining any other work comprised in the authorised development the undertaker must construct any such work within the limits of deviation or extents of work shown on the works plans for the relevant work.