Paragraph 9 I1
England, Wales and Scotland
(1)
No part of the authorised development is to commence until, for that part, a written scheme of investigation of areas of archaeological interest, reflecting the relevant mitigation measures set out in the REAC, has been submitted to and approved in writing by the Secretary of State, following consultation by the undertaker with the relevant planning authority and the Historic Buildings and Monuments Commission for England.
(2)
The authorised development must be carried out in accordance with the scheme referred to in sub-paragraph (1).
Annotations
Commencement
- I1
Sch. 2 para. 9 in force at 13.7.2022, see art. 1