The A47 Wansford to Sutton Development Consent Order 2023 (revoked)
S.I. 2023/218 · Made 17 February 2023 · Extends to England, Wales and Scotland
Infrastructure Planning
Made 17th February 2023
Coming into force 10th March 2023
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Annotations to the whole text
Textual amendments
- F1
Order revoked (3.6.2026) by The A47 Wansford to Sutton Development Consent (Revocation) Order 2026 (S.I. 2026/579), arts. 1, 2
Contents
- Part 1: PRELIMINARY Repealed
- 1Citation and commencement Repealed
- 2Interpretation Repealed
- 3Disapplication of legislative provisions Repealed
- 4Maintenance of drainage works Repealed
- Part 2: PRINCIPAL POWERS Repealed
- 5Development consent etc. granted by the Order Repealed
- 6Maintenance of authorised development Repealed
- 7Planning permission Repealed
- 8Limits of deviation Repealed
- 9Benefit of Order Repealed
- 10Consent to transfer benefit of Order Repealed
- Part 3: STREETS Repealed
- 11Application of the 1991 Act Repealed
- 12Construction and maintenance of new, altered or diverted streets and other structures Repealed
- 13Classification of roads, etc. Repealed
- 14Power to alter layout etc. of streets Repealed
- 15Street works Repealed
- 16Temporary stopping up and restriction of use of streets Repealed
- 17Permanent stopping up and restriction of use of streets and private means of access Repealed
- 18Access to works Repealed
- 19Clearways Repealed
- 20Traffic regulation Repealed
- Part 4: SUPPLEMENTAL POWERS Repealed
- 21Discharge of water Repealed
- 22Protective work to buildings Repealed
- 23Authority to survey and investigate the land Repealed
- Part 5: POWERS OF ACQUISITION Repealed
- 24Compulsory acquisition of land Repealed
- 25Compulsory acquisition of land – incorporation of the mineral code Repealed
- 26Time limit for exercise of authority to acquire land compulsorily Repealed
- 27Compulsory acquisition of rights and imposition of restrictive covenants Repealed
- 28Public rights of way Repealed
- 29Private rights over land Repealed
- 30Modification of Part 1 of the 1965 Act Repealed
- 31Application of the 1981 Act Repealed
- 32Acquisition of subsoil or airspace only Repealed
- 33Rights under or over streets Repealed
- 34Temporary use of land for carrying out the authorised development Repealed
- 35Temporary use of land for maintaining the authorised development Repealed
- 36Statutory undertakers Repealed
- 37Apparatus and rights of statutory undertakers in stopped up streets Repealed
- 38Recovery of costs of new connections Repealed
- Part 6: OPERATIONS Repealed
- 39Felling or lopping of trees and removal of hedgerows Repealed
- 40Trees subject to tree preservation orders Repealed
- Part 7: MISCELLANEOUS AND GENERAL Repealed
- 41Application of landlord and tenant law Repealed
- 42Operational land for purposes of the 1990 Act Repealed
- 43Defence to proceedings in respect of statutory nuisance Repealed
- 44Disregard of certain improvements etc. Repealed
- 45Set off for enhancement in value of retained land Repealed
- 46Protection of interests Repealed
- 47Certification of documents, public register, etc. Repealed
- 48Service of notices Repealed
- 49Arbitration Repealed
- 50Crown Rights Repealed
- 51Removal of human remains Repealed
- Signature
- Schedule 1AUTHORISED DEVELOPMENT Repealed
- Schedule 2: REQUIREMENTS Repealed
- Part 1: REQUIREMENTS Repealed
- 1Interpretation Repealed
- 2Time limits Repealed
- 3Detailed design Repealed
- 4Environmental Management Plan Repealed
- 5Landscaping Repealed
- 6Contaminated land and groundwater Repealed
- 7Protected species Repealed
- 8Surface and foul water drainage Repealed
- 9Flood compensatory storage Repealed
- 10Archaeological remains Repealed
- 11Traffic management Repealed
- 12Fencing Repealed
- 13Approvals and amendments to approved details Repealed
- Part 2: PROCEDURE FOR DISCHARGE OF REQUIREMENTS Repealed
- 14Applications made under requirements Repealed
- 15Further information Repealed
- 16Register of requirements Repealed
- 17Anticipatory steps towards compliance with any requirement Repealed
- 18Details of consultation Repealed
- Schedule 3: CLASSIFICATION OF ROADS, ETC Repealed
- 1TRUNK ROADS Repealed
- 2CLASSIFIED C ROADS Repealed
- 3UNCLASSIFIED ROADS Repealed
- 4SPEED LIMITS Repealed
- 5REVOCATIONS & VARIATIONS OF EXISTING TRAFFIC REGULATION ORDERS Repealed
- 6FOOTPATHS, CYCLE TRACKS, FOOTWAYS AND BRIDLEWAYS Repealed
- 7ROADS TO BE DETRUNKED Repealed
- 8TRAFFIC REGULATION MEASURES (CLEARWAYS AND PROHIBITIONS) Repealed
- Schedule 4PERMANENT STOPPING UP OF HIGHWAYS AND PRIVATE MEANS OF ACCESS & PROVISION OF NEW HIGHWAYS AND PRIVATE MEANS OF ACCESS Repealed
- 1HIGHWAYS TO BE STOPPED UP FOR WHICH NO SUBSTITUTE IS TO BE PROVIDED Repealed
- 2HIGHWAYS TO BE STOPPED UP FOR WHICH A SUBSTITUTE IS TO BE PROVIDED AND NEW HIGHWAYS WHICH ARE OTHERWISE TO BE PROVIDED Repealed
- 3PRIVATE MEANS OF ACCESS TO BE STOPPED UP FOR WHICH A SUBSTITUTE IS TO BE PROVIDED AND NEW PRIVATE MEANS OF ACCESS WHICH ARE OTHERWISE TO BE PROVIDED Repealed
- 4PRIVATE MEANS OF ACCESS TO BE STOPPED UP FOR WHICH NO SUBSTITUTE IS TO BE PROVIDED Repealed
- 5ALTERATIONS TO PRIVATE MEANS OF ACCESS Repealed
- Schedule 5LAND IN WHICH ONLY NEW RIGHTS ETC. MAY BE ACQUIRED Repealed
- Schedule 6: MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS Repealed
- Compensation enactments Repealed
- 1Paragraph 1 Repealed
- 2Paragraph 2 Repealed
- 3Paragraph 3 Repealed
- Application of Part 1 of the 1965 Act Repealed
- 4Paragraph 4 Repealed
- 5Paragraph 5 Repealed
- Schedule 7LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN Repealed
- Schedule 8: REMOVAL OF HEDGEROWS AND TREES Repealed
- 1REMOVAL OF HEDGEROWS Repealed
- 2REMOVAL OF IMPORTANT HEDGEROWS Repealed
- Schedule 9: PROTECTIVE PROVISIONS Repealed
- Part 1: FOR THE PROTECTION OF ELECTRICITY, GAS, WATER AND SEWAGE UNDERTAKERS Repealed
- 1Paragraph 1 Repealed
- 2Paragraph 2 Repealed
- 3On street apparatus Repealed
- 4Apparatus in stopped up streets Repealed
- 5Protective works to buildings Repealed
- 6Acquisition of land Repealed
- 7Removal of apparatus Repealed
- 8Facilities and rights for alternative apparatus Repealed
- 9Retained apparatus Repealed
- 10Expenses and costs Repealed
- 11Paragraph 11 Repealed
- 12Cooperation Repealed
- 13Cooperation Repealed
- Part 2: FOR THE PROTECTION OF OPERATORS OF ELECTRONIC COMMUNICATIONS CODE NETWORKS Repealed
- 14Paragraph 14 Repealed
- 15Paragraph 15 Repealed
- 16Paragraph 16 Repealed
- 17Paragraph 17 Repealed
- Part 3: FOR THE PROTECTION OF ANGLIAN WATER Repealed
- 18Application Repealed
- 19Interpretation Repealed
- 20On street apparatus Repealed
- 21Schedule of apparatus Repealed
- 22Apparatus in stopped up streets Repealed
- 23Protective works to buildings Repealed
- 24Acquisition of land Repealed
- 25Removal of apparatus Repealed
- 26Facilities and rights for alternative apparatus Repealed
- 27Retained apparatus Repealed
- 28Expenses and costs Repealed
- 29Expenses and costs Repealed
- 30Cooperation Repealed
- 31Cooperation Repealed
- 32Cooperation Repealed
- 33Cooperation Repealed
- Part 4: FOR THE PROTECTION OF NGG AS GAS UNDERTAKER Repealed
- 34Application Repealed
- 35Interpretation Repealed
- 36Interpretation Repealed
- 37Apparatus of NGG in stopped up streets Repealed
- 38Protective works to buildings Repealed
- 39Acquisition of land Repealed
- 40Removal of apparatus Repealed
- 41Facilities and rights for alternative apparatus Repealed
- 42Retained apparatus: protection of gas undertaker Repealed
- 43Expenses Repealed
- 44Indemnity Repealed
- 45Enactments and agreements Repealed
- 46Co-operation Repealed
- 47Access Repealed
- 48Arbitration Repealed
- 49Notices Repealed
- Part 5: FOR THE PROTECTION OF NATIONAL GRID ELECTRICITY TRANSMISSION PLC AS ELECTRICITY UNDERTAKER Repealed
- 50Application Repealed
- 51Interpretation Repealed
- 52Paragraph 52 Repealed
- 53Apparatus of National Grid in stopped up streets Repealed
- 54Protective works to buildings Repealed
- 55Acquisition of land Repealed
- 56Removal of apparatus Repealed
- 57Facilities and rights for alternative apparatus Repealed
- 58Retained apparatus: protection of electricity undertaker Repealed
- 59Expenses Repealed
- 60Indemnity Repealed
- 61Enactments and agreements Repealed
- 62Co-operation Repealed
- 63Access Repealed
- 64Arbitration Repealed
- 65Notices Repealed
- Part 6: FOR THE PROTECTION OF NATIONAL GRID ELECTRICITY DISTRIBUTION (EAST MIDLANDS) PLC AS ELECTRICITY UNDERTAKER Repealed
- 66Application Repealed
- 67Interpretation Repealed
- 68Precedence of 1991 Act in respect of apparatus in streets Repealed
- 69No acquisition except by agreement Repealed
- 70Removal of apparatus Repealed
- 71Facilities and rights for alternative apparatus Repealed
- 72Retained apparatus Repealed
- 73Expenses and costs Repealed
- 74Expenses and costs Repealed
- 75Expert determination Repealed
- Schedule 10: DOCUMENTS TO BE CERTIFIED Repealed
- 1ENVIRONMENTAL STATEMENT Repealed
- 2OTHER DOCUMENTS Repealed
- Explanatory note