Paragraph 1 InterpretationI1
England, Wales and Scotland
In this Schedule—
“CEMP” means the construction environmental management plan, being the EMP as approved prior to the construction of the authorised development;
“EMP” means the environmental management plan referred to in paragraph 4(1);
“environmental statement” means the document certified as the environmental statement under article 34 (certification of plans, etc.) for the purposes of this Order;
F1“European protected species” has the same meaning as in regulations 42 and 46 of the Conservation of Habitats and Species Regulations 2017; and
“HEMP” means the handover environmental management plan, being the EMP to be developed towards the end of the construction of the authorised development to contain—
- (a)
the environmental information needed for the future maintenance and operation of the authorised development;
- (b)
the long-term commitments to aftercare, monitoring and maintenance activities relating to the environmental features and mitigation measures that will be required to ensure the continued long-term effectiveness of the environmental mitigation measures and the prevention of unexpected environmental impacts during the operation of the scheme; and
- (c)
a record of the consents, commitments and permissions resulting from liaison with statutory bodies including Natural England.
- (a)
Annotations
Textual amendments
- F1
Words in Sch. 2 para. 1 substituted (30.11.2017) by The Conservation of Habitats and Species Regulations 2017 (S.I. 2017/1012), reg. 1(2), Sch. 6 para. 37
Commencement
- I1
Sch. 2 para. 1 in force at 18.9.2014, see art. 1