Paragraph 13 I1

England, Wales and Scotland

(1)

No part of the authorised development is to commence until for that part a Piling Design Statement has been submitted to and approved in writing by the Secretary of State, following consultation with the relevant planning authority on matters related to their functions.

(2)

The authorised development must be carried out in accordance with the Piling Design Statement approved under sub-paragraph (1).

(3)

The Piling Design Statement prepared under sub-paragraph (1) must include details of—

(a)

options for the proposed piling method at each location where piling is proposed;

(b)

for each piling method option at each location, noise and vibration mitigation measures and anticipated noise and vibration effects on identified receptors that are likely to be affected;

(c)

the proposed piling method and noise and vibration mitigation measures at each location; and

(d)

justification of why rotary bored piling is not feasible in any location where the use of percussive piling would lead to more adverse noise or vibration effects on the identified receptors that are likely to be affected.

Annotations

Commencement

I1

Sch. 2 para. 13 in force at 7.12.2022, see art. 1