Article 12 Amendment to Schedule 2 (permanent stopping up of highways and private means of access and provision of new highways and private means of access)

Original text. Later amendments are not shown.

In the table in Part 3 of Schedule 2 that relates to Scheme 0405 (Temple Sowerby to Appleby) in the section headed Scheme 0405 – The rights of way and access plans – sheets 3 and 4—

(a)

in row 11 in column (4), in the entry headed “Reference 49”—

(i)

for “135 metres” substitute “144 metres”;

(ii)

for “45 metres” substitute “292 metres to Point L”;

(iii)

for “255 metres towards the new A66” substitute “78 metres”; and

(iv)

for “300 metres” substitute “812 metres”; and

(b)

in row 12 in column (4) in the entry headed “Reference 50”, for “85 metres” substitute “135 metres”.