Paragraph 54 Specified WorksI1
England, Wales and Scotland
Not less than 28 days before starting the execution of any specified work in, on or under any land purchased, leased, held, appropriated or used under this Order that are within 6 metres of any apparatus, or will or may affect any apparatus, the undertaker must submit to the solar operator a plan, section and description of the specified works to be executed.
Those specified works must be executed only in accordance with the plan, section and description submitted under sub-paragraph (1) and in accordance with such reasonable requirements as may be made in accordance with sub-paragraph (3) by the solar operator for the alteration or otherwise for the protection of the apparatus, or for securing access to it, and the solar operator is entitled to watch and inspect the execution of those specified works.
Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 28 days before commencing the execution of any specified works, a new plan, section and description instead of the plan, section and description previously submitted, and having done so the provisions of this paragraph apply to and in respect of the new plan, section and description.
The undertaker is not required to comply with sub-paragraph (1) in a case of emergency but in that case it must give to the solar operator notice as soon as is reasonably practicable and a plan, section and description of those specified works as soon as reasonably practicable subsequently and must comply with sub-paragraph (2) in so far as is reasonably practicable in the circumstances.
Annotations
Commencement
- I1
Sch. 11 para. 54 in force at 10.10.2019, see art. 1
Notes on Schedule 11
Footnotes
- f1
-
The protective provisions within this Schedule are draft protective provisions and are being discussed with the relevant statutory undertaker.