Paragraph 16 Peat Management PlanI1
England, Wales and Scotland
(1)
Where the site investigation report carried out in accordance with requirement 14 confirms the presence of peat affecting relevant parts of numbered work 5, affected parts of numbered work 5 must not commence until a peat management plan covering the affected parts has been submitted to and approved in writing by the relevant planning authority in consultation with Natural Resources Wales.
(2)
All construction works must be undertaken in accordance with the approved peat management plan.
Annotations
Commencement
- I1
Sch. 2 para. 16 in force at 10.10.2019, see art. 1