OpenLegislation

Paragraph 19 Pollution prevention management planI1

England, Wales and Scotland

(1)

Numbered work 5 of the authorised development must not commence until a pollution prevention management plan covering that numbered work has been submitted to and approved in writing by the relevant planning authority, in consultation with Natural Resources Wales. The pollution prevention management plan must be substantially in accordance with the contents outlined in the outline construction environmental management plan and must include details of a complaints procedure and details of any artificial lighting proposed during construction of numbered work 5.

(2)

All construction works must be undertaken in accordance with the approved pollution prevention management plan.

Annotations

Commencement

I1

Sch. 2 para. 19 in force at 10.10.2019, see art. 1